PalaRaiffeisen gets its dates: handover in February, grand opening in September 2027
The city has announced the calendar for the new Cornaredo sports hall: a first test on 5 and 6 June 2027 with the Swiss fencing championships, then four public opening days from 9 to 12 September. Handover moves from 30 November 2026 to 26 February 2027.
Translated from the Italian original. Read in Italian
Lugano's new sports hall now has a complete calendar. On Friday 20 November the city announced the three dates that mark the final stretch of the PalaRaiffeisen construction site in the Cornaredo quarter: the building will be handed over to the city on 26 February 2027, its first sports event will follow on 5 and 6 June 2027 with the Swiss fencing championships, and the public opening is set for 9 to 12 September 2027, with four days of Grand Opening celebrations.
The handover date is not the one originally planned. The initial deadline was 30 November 2026. The postponement of almost three months was already on the table in the fourth half-yearly report on the Sports and Events Centre, sent to the city parliament on 23 July, when the city and general contractor HRS SA were evaluating the move. The report cited about thirty days lost to adverse weather, plus the time to complete the finishing works, test the building and train its staff. Yesterday's announcement makes the new date final.
Fencing puts it to the test first, then the party
Fencers will be the first to compete in the hall. The Swiss championships of 5 and 6 June 2027 will serve as the test event: the first national competition hosted in the building will put its spaces, systems and operating procedures through their paces in front of a real crowd. The Lugano date also appears in the provisional 2026/27 calendar of the Swiss Fencing federation, which lists the national championships in Lugano that weekend. Three months later, from 9 to 12 September, the Grand Opening will welcome the public for four days of discovery. The detailed inauguration programme and further test event particulars will be announced later.
In the meantime the building can be visited virtually: the official site, palaraiffeisen.ch, offers an interactive three-dimensional model of its floors and spaces, and an Instagram profile posts updates and previews. According to the venue's site, the main hall measures 1,940 square metres, the building will stay open 365 days a year and seven sports clubs will be resident.
Three thousand seats for sport, four thousand for events
The PalaRaiffeisen is the sports hall of the first phase of the Sports and Events Centre. At the laying of the first stone in September 2024, the city presented it as the new home of about a thousand athletes in basketball, volleyball, gymnastics, fencing, table tennis, judo and rhythmic gymnastics. Its multifunctional gym holds 3,000 spectators for competitions and converts into a triple gym for training; beside it sit a double gym, discipline-specific spaces, recovery and fitness rooms and the offices of the Sports Division and the clubs.
For non-sporting events the capacity rises to 4,000 people, with 1,600 seated and 2,400 standing. The name comes from the naming-rights agreement with the Raiffeisen banks of the Lugano district, partners for the construction years and the first five management years, from 2027 to 2031, with an option for five more, the financial support going entirely to the sports societies.
The July report described a building now closed in: reinforced concrete structures and the steel roof complete, the facade and window frames being finished and, inside, the GlassFloor of the triple gym laid in June, its LED court lines reconfigurable for each discipline. The retractable mobile stands were still to be installed. The building's cost, in the cost ceiling updated at 30 June 2026, is CHF 77,600,067, within an overall ceiling for the centre of CHF 191,584,186 including VAT.
The stadium, the other sporting half of the first phase, is in service: final occupancy permit on 30 April 2026, the Swiss Football League's final inspection and the UEFA test match of 5 June passed, and more than 10,000 people at its open days on 30 and 31 May. Around it, the quarter keeps growing: excavation for the second phase has begun, with the two towers, the municipal police services block, the south building and the urban park, and the venue's site describes a 130,000 square metre quarter that by the end of 2029 will become a new district of the city.
PalaRaiffeisen in dates and figures
| Handover to the city | 26 February 2027 | City of Lugano, 20 Nov 2026 |
| First test event | Swiss fencing championships, 5 and 6 June 2027 | City of Lugano, 20 Nov 2026 |
| Grand Opening | 9 to 12 September 2027 | City of Lugano, 20 Nov 2026 |
| Competition capacity | 3,000 spectators | City of Lugano, 24 Sep 2024 |
| Maximum event capacity | 4,000 people | City of Lugano, 24 Sep 2024 |
| Building cost | CHF 77,600,067 | City of Lugano, report of 23 Jul 2026 |