Lugano-Agno airport: the city proposes a partnership with private investors

Two executive messages to the city parliament: CHF 540,000 to prepare an investor competition, with private partners expected to put CHF 60 to 65 million into the airport buildings, and CHF 2.24 million for the runway and its lights. Operations stay public.

By Lugano Tribune November 20, 2026, 05:30

Translated from the Italian original. Read in Italian

Lugano-Agno airport in a 2022 view: the runway on the Magadino plain, between Agno, Bioggio and Muzzano, with the lake and the Lugano hills.
Lugano-Agno airport in a 2022 view: the runway on the Magadino plain, between Agno, Bioggio and Muzzano, with the lake and the Lugano hills. Foto: Adrian Michael, via Wikimedia Commons (CC BY-SA 3.0)

This article was translated from the Italian edition of Lugano Tribune.

The future of Lugano-Agno airport runs through a deal between the public owner and private investors, with the city keeping its hand on the controls. Lugano's city executive has sent two messages to the city parliament: the first designs a public-private partnership to renew the airport's infrastructure and asks for CHF 540,000 for the studies and advice needed to prepare land acquisitions, an investor competition and the partnership agreements; the second allocates CHF 2,243,000 to two urgent jobs on the runway and the lighting systems. Both figures include VAT.

The apron with the control tower and the terminal: the landside buildings, from the terminal to the hangars, are the ones the partnership would entrust to private partners.
The apron with the control tower and the terminal: the landside buildings, from the terminal to the hangars, are the ones the partnership would entrust to private partners. Foto: Justus Weiss, via Wikimedia Commons (CC BY-SA 3.0)

The division of labour is clear-cut. The city will keep the federal concession and operational management: it stays responsible for developing, financing and running the runway, the taxiways and the aprons, and for setting the airport's strategic direction. Private partners would finance, build and manage the landside buildings, those outside the operating areas: the terminal, the offices, the control tower and the hangars. The total investment is estimated at CHF 60 to 65 million, borne entirely by the private side.

The legal vehicle is the building right: most of the land is municipally owned, and the buildings the airport needs would be leased back to the city, which could buy them from completion onwards and at any later time. In return the city would collect fees for the building rights and for the service concessions granted to operators. The executive's stated aim is to mobilise private capital and skills to modernise dated infrastructure and bring it up to current standards and operators' expectations.

A turboprop parked on the Agno apron in a February 2018 photograph, with business jets behind: business aviation is the segment the project aims to grow.
A turboprop parked on the Agno apron in a February 2018 photograph, with business jets behind: business aviation is the segment the project aims to grow. Foto: Thomas Woodtli, via Wikimedia Commons (CC BY-SA 2.0)

Urgent works: turnpad and lights by 2027

The second message looks at keeping the airport running in 2027 and 2028. The CHF 2,243,000 pays for a turnpad at the southern end of the runway, so that larger aircraft can manoeuvre safely, and for renewing the runway and taxiway lighting, in service since 2002 and partly at the end of its useful life. These are not deferrable works: they answer prescriptions of the Federal Office of Civil Aviation, which has set 31 December 2027 as the expiry of the derogation linked to the missing turnpad. They are city investments, needed whatever development model the airport follows.

From transitional management to a concession running to 2056

The two messages close the phase opened in 2020, when Lugano Airport SA entered orderly liquidation and its activities and staff passed to the city, which owns the site and holds the federal concession. The transitional arrangement has lasted since then. A first attempt to bring in private partners, the September 2020 call for expressions of interest, was abandoned in August 2023 because it could no longer serve as a reasonable and legally sound basis for awarding the management. What now gives the project its long horizon is the thirty-year renewal of the operating concession, granted by the federal transport department last September and valid until 15 September 2056.

The project aims in particular at business aviation, with infrastructure and services fitted to that segment's operators. It also leaves open the possibility of restoring an air link between Lugano and Geneva, in light of the ongoing revision of the federal aviation act, which could allow cabotage: domestic Swiss flights operated by foreign carriers with aircraft suited to Agno's characteristics. The announced calendar puts the investor competition in 2027 and 2028, ratification of the land acquisitions and the partnership agreement in 2028 and 2029, and a phased build with minimal disruption. A first phase, with the terminal, offices, airport services and part of the hangars, should enter service in 2033; the second, centred on most of the new hangars, would start in 2035. The city parliament now has to vote on the two credits.